India · English
Paid Rs 2.06 cr, got no flat; Court rejects builder’s delay argument, orders interest
Two homebuyers filed a case against the builder. The dispute concerned an apartment for which they had signed the sale agreement in 2014, with possession due by June 30, 2017. The flat's consideration was Rs 1.95 crore. By the time of the complaint, the buyers had paid Rs 2.06 crore, including the consideration paid to the promoter, stamp duty, registration charges and applicable taxes.
Read the full report at Times of India Top →
About this page
AKHBAARI groups the same story across publishers so you can see who is reporting it and how they differ. The summary above is machine-generated from the publisher's own feed text and is labelled as such. The full report stays with the publisher, who holds copyright in it. See our editorial policy.